No EOT for Concurrent Delay, if so Agreed

Contract clauses that deny a contractor entitlement to an extension of time for concurrent delays caused by both employer and contractor are valid in principle.  In North Midland Building Ltd -V- Cyden Homes Ltd [1] the Court of Appeal of England and Wales has ruled that such clauses do not offend the common law prevention principle.  Nor do they give rise to an implied term to prohibit the imposition of delay damages that may result.

By |21/05/2019|Delay, English Law, featured, Knowledge Hub|Comments Off on No EOT for Concurrent Delay, if so Agreed