FIDIC 1999 Books – Commentary on Clause 20
Summary Clause 20 deals with claims, disputes and arbitration. Sub-Clause
Summary Clause 20 deals with claims, disputes and arbitration. Sub-Clause
FIDIC ‘launched’ the FIDIC 2022 reprints at the FIDIC International Construction Users’ Conference 2022, in London. The reception to the changes was mixed – some embraced the clarity; others questioned the significance and cost. This article draws your attention to 10 of the key areas of change in respect of the FIDIC Red Book 2017 including the definition of Claim, matters to be agreed or determined, the definition of Dispute and Exceptional Events.
Although Clause 17 is titled ‘Risk and Responsibility’ it also sets out other provisions relating to indemnities, limitation of liability and, unusually, the specific topic of intellectual and industrial property rights. The clause provides that the Contractor assumes responsibility and bears the risk for the care of the works during execution and for remedying any defects during the Defects Notification Period. Risk transfers to the Employer on issue of the Taking–Over Certificate to the extent of works defined as being completed. Generally, in construction contracts ‘risk’ is understood to mean an event or circumstance which causes delay, loss or damage to the Works. A risk can be said to be Employer caused, Contractor caused or neutral. The purpose of risk allocation is to determine which party bears the risk for such events. The Contractor may be required to remediate the damage at his own cost or the Employer may be required to pay for the damaged works. It has been stated that the “FIDIC standard forms are generally recognised as being well balanced because both parties bear parts of the risks arising from the project.”
FIDIC’s 2017 editions introduced a new Claims management system in clause 20 that channels Claims through two very different procedures. One of them is very simple and involves almost no risk whereas the other will require investment of significant project resources, will take the parties a considerable amount of time to resolve and carries fatal consequences if not followed properly. It has therefore become a priority for anyone handling this Claims management system to understand how clause 20.1 sorts the different types of Claims and to recognise that the classification scheme is not as straightforward as the wording of the Contract suggests, as explored in this article.
Clause 14 deals with all aspects of payment. It also deals with the Statement at Completion, the Final Payment Certificate, Discharge and Cessation of the Employer’s Liability. The Clause provides that this is a re-measurement contract and that the quantities stated in the Bill of Quantities are estimated. There is provision for an advance payment to be made to the Contract. Applications for Interim Payment Certificates are made monthly and these must be supported by documents and a report on progress. Unless the amount assessed is less than the minimum amount set out in the Appendix to Tender, the Engineer has 28 days to issue an Interim Payment Certificate, which states the amount the Engineer fairly determines to be due. The Employer thereafter has an obligation to pay the amount certified, in the currencies named in the Appendix to Tender. In the event that payment is not received the Contractor can claim financing charges compounded monthly. Fifty per cent of the retention monies are paid when the Taking-Over Certificate is issued. Where there are Sections then a proportion is paid. The balance of retention is paid on the expiry of the latest Defects Notification Period or, where there are Sections, a proportion at the expiry of the Defects Notification Period for that Section. Within 84 days of receiving the Taking-Over Certificate the Contractor submits a Statement at Completion. This must include an estimate of all sums which the Contractor considers due. Within 56 days of receiving a Performance Certificate, the Contractor submits a Final Statement. The Contractor must also submit with the Final Statement a written discharge which confirms that the total of the Final Statement represents full and final settlement of all moneys due. The Engineer then issues to the Employer a Final Payment Certificate. The Contract states that the Employer shall have no liability to the Contractor except to the extent that the Contractor has included an amount expressly for that matter in the Final Statement and also the Statement at Completion.
Clause 3 deals with the duties and obligations of the Engineer and his assistants. Sub-Clause 3.1 deals with the role and duties of the Engineer. The Engineer is deemed to act for the Employer. The Engineer has no authority to relieve the Contractor of his duties, obligations or responsibilities under the Contract; nor can the Engineer amend the Contract. Under Sub-Clause 3.2 the Engineer can delegate authority to any assistants; however, the Engineer cannot delegate the responsibility to make Determinations. Under Sub-Clause 3.3 the Engineer may issue instructions or modified Drawings at any time, which are necessary for the execution of the Works. If the instruction constitutes a Variation, then it is dealt with under Clause 13 [Variations and Adjustments]. The Contractor is required to comply with any instruction given by the Engineer or delegated assistant. Sub-Clause 3.4 deals with the replacement of the Engineer. The Employer must not replace the Engineer with someone against whom the Contractor raises reasonable objection. Sub-Clause 3.5 deals with Determinations. When making a Determination the Engineer should consult with each of the Parties and, if agreement cannot be reached, make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances. Both Parties are required to give effect to any Determination unless, or until, it is revised under Sub-Clause 20.1 [Claims, Disputes and Arbitration].
The 1999 Clause 20 has now been divided into Clauses 20 and 21 whereby Clause 20 refers to Claims and Clause 21 refers to Disputes and Arbitration. Another main upgrade is that Employer’s Claims now need to follow the same procedure. The main list of Employer’s and Contractor’s Claims is as follows: a. Additional payment; b. Reduction in the Contract Price; c. Extension of the DNP; and d. Extension of time.
The main changes: Employer’s consent and neutrality The main changes in Clause 3 are the express provisions in Sub-Clause 3.2 [Engineer’s Duties and Authority] that the Engineer is not required to obtain the Employer’s consent before the Engineer exercises its authority under Sub-Clause 3.7 [Agreement or Determination], and that the Engineer must act “neutrally” when exercising its duties under Sub-Clause 3.7 [Agreement or Determination]. Dictionary definitions suggest that “neutrally” is similar in meaning to the words “independently” or “impartially” found in the FIDIC Red Book 4th edition and the FIDIC Yellow Book 3rd edition. However, the drafting committee believe that by using a different word it will avoid the difficulties raised in the interpretation of independently or impartially in the earlier editions. This remains to be seen. The intention is that “the Engineer treats both Parties even-handedly, in a fair minded and unbiased manner”.
Clause 2 now has 6 sub-clauses: Employer’s claims has been removed to clause 20; and new provisions 2.5 [Site Data and Items of Reference] and 2.6 [Employer-Supplied Materials and Employer’s Equipment] have been added. The obligations to provide possession, access and assistance with permits etc. are essentially the same, as are the consequences of failure to do so. The main change to clause 2.4 [Employer’s Financial Arrangements] is that the Employer now sets out his arrangements in the Contract Data; and the Contractor can only request evidence of ability to pay if those arrangements change, there is non-payment or there are variations in excess of 30% or a single variation over 10%.
In London last week, FIDIC launched its Second Editions of the Red, Yellow and Silver Books. They are big, weighing in at almost a kilo each. The general conditions cover 106 pages with more than 50,000 words, over 50% longer than the 1999 forms. Many improvements have been made, addressing issues that have emerged since 1999. Fans of Dispute Boards will be pleased to see that all three books now have standing boards with more emphasis on dispute avoidance; and that appointment of DB members and enforcement of their decisions have been made easier. Disputes and Arbitration are now dealt with in a separate chapter 21. Here are the most interesting changes to the Yellow Book.