FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

Up until the spring of 2020, a FIDIC 1999 Sub-Clause 13.7 [Adjustments for Changes in Legislation][1] claim was just one of many issues to be resolved, for example, in a delay and disruption claim or a Cost claim. However, the focus it receives in the context of Covid-19 is drastically different. Many in the industry are using the changes in legislation provision to seek financial compensation in a situation that would otherwise potentially only attract an extension of time.[2] Awarding Cost for Covid-19 events regardless of the circumstances may seem to some (Contractors mostly, though there are Employers and Engineers who agree) like the appropriate thing to do, but whether it is correct according to the Contract is a different question.

By |23/09/2021|Covid, Delay, featured, Knowledge Hub|Comments Off on FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

FIDIC’s Emerald Book – A contractor’s charter or optimum risk allocation?

It has been suggested that FIDIC’s new Emerald Book may be “a contractors’ charter for riches”. 1 This article examines whether this new form of contract for underground works by FIDIC and the International Tunnelling and Underground Space Association is too contractor-biased or whether it provides a sensible and pragmatic risk allocation process, in an area of construction and engineering which is well known for claims. If more risks are placed on the Employer in this form of contract, what are the benefits of the contract compared to, for example, an unamended FIDIC Yellow Book?

By |10/03/2020|Arbitration, featured, Knowledge Hub|Comments Off on FIDIC’s Emerald Book – A contractor’s charter or optimum risk allocation?

No EOT for Concurrent Delay, if so Agreed

Contract clauses that deny a contractor entitlement to an extension of time for concurrent delays caused by both employer and contractor are valid in principle.  In North Midland Building Ltd -V- Cyden Homes Ltd [1] the Court of Appeal of England and Wales has ruled that such clauses do not offend the common law prevention principle.  Nor do they give rise to an implied term to prohibit the imposition of delay damages that may result.

By |21/05/2019|Delay, English Law, featured, Knowledge Hub|Comments Off on No EOT for Concurrent Delay, if so Agreed

FIDIC 1999 Books – Commentary on Clause 8

Clause 8 contains all the fundamental provisions relating to the start of the Works, the Time for Completion, delays and the entitlement of the Contractor to an extension of time and of the Employer to delay damages, and finally the circumstances in which a suspension of the Works can occur and the implications for the Parties. 

By |14/11/2018|Delay, English Law, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 8

FIDIC 2017 – First Impressions of the 3-Kilo Suite

In London last week, FIDIC launched its Second Editions of the Red, Yellow and Silver Books. They are big, weighing in at almost a kilo each. The general conditions cover 106 pages with more than 50,000 words, over 50% longer than the 1999 forms. Many improvements have been made, addressing issues that have emerged since 1999. Fans of Dispute Boards will be pleased to see that all three books now have standing boards with more emphasis on dispute avoidance; and that appointment of DB members and enforcement of their decisions have been made easier. Disputes and Arbitration are now dealt with in a separate chapter 21. Here are the most interesting changes to the Yellow Book.

By |13/12/2017|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 2017 – First Impressions of the 3-Kilo Suite
Go to Top