The main changes to Clause 5 are as follows:
-
- finding that the Contractor’s Document fails to comply with the Employer’s Requirements; or
- giving No-objection (although he may include comments concerning minor matters which will not substantially affect the Works).
- In Sub-Clause 5.8 [Design Error], a new procedure has been put in place that provides that if errors, omissions, ambiguities, inconsistencies, inadequacies, or other defects are found which were previously the subject of a No-objection, then the process set out for a failure under Sub-Clause 5.2.2 should be engaged, hence giving the Contractor a process for revising and re-submitting the Contractor’s Documents.
Please get in touch at [email protected] or [email protected] with your thoughts or to discuss any concerns.
INSIGHTS
2017 Suite: Commentary on Clause 05 – Design
13/11/2024
Get in touch
INSIGHTS
2017 Suite: Commentary on Clause 05 – Design
November 13, 2024
Get in touch
The main changes to Clause 5 are as follows:
Under the 1999 Edition, in relation to documents submitted to it for approval, the Engineer essentially had 3 options:
Please get in touch at [email protected] or [email protected] with your thoughts or to discuss any concerns.