FIDIC 1999 Books – Commentary on Clause 2

Corbett & Co. has devised a helpful commentary on FIDIC 1999 books Clause 2. Clause 2 sets out certain obligations which are imposed on the Employer; however, this is by no means all the Employer’s obligations. The obligation to pay the Contractor, for example, is found in Sub-Clause 14.7 and the obligation to Take-Over the Works is found at Sub-Clause 10.1. The first obligation imposed on the Employer under this Clause is to give to the Contractor a right of access. Sub-Clause 2.1 needs to be read alongside Sub-Clauses 2.3 and 4.6, which make it clear that possession of the Site need not be exclusive. Sub-Clause 2.2 imposes on the Employer an obligation to assist the Contractor when requested to obtain permits, licences or approvals required by the laws of the Country. The obligation to reasonably assist is not an absolute obligation and generally will not mean the Employer will have to expend money on fulfilling the obligation. Sub-Clause 2.3 imposes on the Employer an obligation similar to that imposed on the Contractor under Sub-Clause 4.6. The Employer is responsible for any failure by its personnel to co-operate with the Contractor or to comply with safety regulations, take care of persons on Site, make sure the Site is reasonably free from unnecessary obstructions, and protect the environment. Sub-Clause 2.4 imposes on the Employer an obligation to show that financial arrangements have been made and are in place to enable it to pay the Contract Price. Sub-Clause 2.5 deals with the Employer’s Claims and requires that the Employer give notice and particulars of its claim before the Engineer makes a Determination under Sub-Clause 3.5. The Employer cannot set-off any claims it may have against the Contractor unless it complies with this Sub-Clause.

By |27/11/2024|Dispute Boards, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 2

FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC ‘launched’ the FIDIC 2022 reprints at the FIDIC International Construction Users’ Conference 2022, in London. The reception to the changes was mixed – some embraced the clarity; others questioned the significance and cost. This article draws your attention to 10 of the key areas of change in respect of the FIDIC Red Book 2017 including the definition of Claim, matters to be agreed or determined, the definition of Dispute and Exceptional Events.

By |18/01/2023|Adjudication / Dispute Boards / ADR, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC contracts—introduction to the FIDIC Green Book 2021

This Practice Note is an introduction to the FIDIC Green Book 2021 (the Short Form of Contract). It is not a fully detailed clause-by-clause commentary. This article was first published by LexisPSL

By |10/01/2023|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC contracts—introduction to the FIDIC Green Book 2021

Escalating construction costs under FIDIC: is Sub-Clause 13.8 an answer?

Construction costs are escalating. Under existing contracts, an employer will not want to pay more for the works. But forcing a contractor to perform works that are unprofitable or causing a massive loss is unlikely to be in the best interests of the project. It may result in the insolvency of the contractor forcing the employer to abandon the contract or re-let it, probably at a premium. Is a mechanism for cost adjustment, such as FIDIC 1999 Sub-Clause 13.8 [Adjustments for Changes in Costs], an answer?

By |30/08/2022|Cost, featured, Knowledge Hub|Comments Off on Escalating construction costs under FIDIC: is Sub-Clause 13.8 an answer?

Price escalation and FIDIC: is Force Majeure an answer?

Could provisions in FIDIC contracts giving relief for ‘Force Majeure’ or ‘Exceptional Events’ provide relief to contractors suffering as a result of price escalation? It is well documented that construction and engineering projects around the globe are being affected by extreme and sometimes unprecedented price escalation. This is for many reasons including the Covid-19 pandemic and the Russo-Ukrainian conflict.

By |30/08/2022|Cost, featured, Knowledge Hub|Comments Off on Price escalation and FIDIC: is Force Majeure an answer?

FIDIC’S Golden Principles – holding back the tide?

FIDIC is concerned about its image. It says that heavily amending the FIDIC forms of contract impacts upon the FIDIC brand and that this is damaging FIDIC’s reputation. It seeks to address this with the introduction of five Golden Principles. But the Golden Principles are merely aspirational; they are not binding and have no contractual effect. Does this render them a pointless gesture ‘trying to hold back the tide’?

By |10/03/2020|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC’S Golden Principles – holding back the tide?
Go to Top