Found 132 Results
Page 2 of 6

2017 Suite: Commentary on Clause 13 – Variations and Adjustments


Clause 13 clarifies the Engineer’s power to vary, allowing contractors to object to unforeseeable variations. Significant limitations include objections for health, safety, and environmental impacts. Variations must align with Employer’s Requirements, and supplemental agreements may be needed for significant changes.

Author:

Tags: , , , ,

11/13/2024


2017 Suite: Commentary on Clause 12 – Tests after Completion


Clause 12 covers Tests after Completion, often required for process and power contracts. Tests are conducted by the Employer, with significant changes including competent staff requirement, testing per Employer’s Requirements and O&M Manuals, and new provisions for test timing and notice.

Tags: , , , , ,


2017 Suite: Commentary on Clause 11 – Defects After Taking Over


Clause 11 has been clarified, with detailed provisions for notices and periods, DNP for Parts, and clearer time limits. Changes include risk allocation, compensation for denied access, and limited liability for Plant damage. Some cross-references may cause confusion.

Author:

Tags: , , , , ,


2017 Suite: Commentary on Clause 07 – Plant, Materials and Workmanship


Clause 7 of FIDIC 2017 mandates specified quality for plant, materials, and workmanship, requiring defect rectification. It covers testing, inspection, and rejection to ensure compliance. All sub-clauses have changed, with several significant modifications.

Author:


1999 Suite: Commentary on Clause 16 – Suspension and Termination by Contractor


Clause 16 addresses suspension and termination by the Contractor, including rights to suspend work, grounds for termination, cessation of work, and payment on termination. It specifies notice periods, conditions for immediate termination, and entitlements following termination.

Author:

Tags: , , , , , ,


1999 Suite: Commentary on Clause 12 – Measurement and Evaluation


FIDIC 1999 is a re-measurement contract, with the Employer bearing the risk of quantity variations. Clause 12 covers measurement, evaluation of rates, and valuation of omissions. It lacks a standard measurement method, which has been criticized.

Author:

Tags: , , , , , ,


1999 Suite: Commentary on Clause 09 – Tests on Completion


Clause 9 covers Tests on Completion, requiring the Contractor to give notice when ready to carry out Tests on Completion, addressing delays by either party, retesting after failure, and handling failures to meet contract requirements after retesting.

Author:

Tags: , , , ,



BoQ Rates Neither ‘Immutable nor Sacrosanct’


The Hong Kong Court of Appeal now supports engineers requesting evidence of original tender build-up and disallowing loaded rates if substantial quantity differences justify it. This article explores that new guidance, which finds contract rates to be neither immutable nor sacrosanct.

Author:

Tags: , , , , ,


1999 Suite: Commentary on Clause 04 – The Contractor


Clause 4 of the FIDIC Red Book 1999 consolidates various Contractor obligations, covering 24 topics. It includes general duties and references other significant obligations scattered throughout the Contract, such as communications, assignment, document care, compliance with laws, and time for completion.

Author:


2017 Suite: Commentary on Clause 05 – Design


Clause 5 changes include specifying designer qualifications, moving part of Sub-Clause 5.1 to 1.9, changing “approval” to “No-objection” in Sub-Clause 5.2, and introducing a new procedure for addressing design errors in Sub-Clause 5.8.

Author:


2017 Suite: Commentary on Clause 04 – The Contractor


Clause 4 changes include defining ‘fitness for purpose’ in Employer’s Requirements, adjusting the Performance Security, handling communications by the Contractor’s Representative, setting subcontracting limits, enhancing health and safety obligations, redefining unforeseeable conditions, and increasing Contractor risk for access routes.

Author:


Are ‘binding’ DAB decisions enforceable?


Opinions on enforcing ‘binding’ DAB decisions vary. Some arbitrators support enforcement, while others, including the Singapore Court of Appeal, oppose it. This article considers case law addressing both sides of the argument and the issues that they raise.

Author:

Tags:



‘Taking-Over’ in the FIDIC Red Book 1999: Common Problems


A Taking-Over Certificate in FIDIC contracts marks the handover date of Works to the Employer, who cannot use them until issued. Disputes arise in tough economies, with Employers delaying responsibility and Contractors eager to finish and reduce costs.

Author:

06/04/2024


FIDIC Dispute Board Decisions: Late for a Very Important Date?


A FIDIC dispute board has just 84 days to give […]

Author:


FIDIC Green Book 2021 – Short and Simple?


As one of the drafters of the Green Book 1999, […]

Author:


1999 Suite: Commentary on Clause 10 – Employer’s Taking Over


Clause 10 covers the Taking-Over of Works, Sections, or parts. It includes conditions for Taking-Over, deemed Taking-Over due to Employer’s use or interference, and breach of contract if the Engineer fails to issue the Taking-Over Certificate.

Builders consulting plans

Author:

04/25/2024


1999 Suite: Commentary on Clause 20 – Claims, Disputes, and Arbitration


Clause 20 covers claims, disputes, and arbitration. It includes procedures for Contractor claims, appointing a Dispute Adjudication Board (DAB), handling disputes, amicable settlement, arbitration under ICC rules, and actions when a DAB decision is not complied with or absent.

People signing document at official meeting

Author:

04/24/2024


As simple as it seems? – an analysis of the prolongation costs clause in the FIDIC Green Book 2021


This article reflects on the introduction of an automatic contractual mechanism for calculating prolongation costs into the Green Book 2021 and will consider whether it will remove the expense of experts and lawyers from the process of claiming prolongation costs.

People signing document at official meeting

Author:

11/14/2023


Risks in the Construction of Hydropower Projects: Unforeseen Ground Conditions under FIDIC


Hydropower projects rely heavily on ground conditions, which are often unpredictable despite pre-tender investigations. This article explores how FIDIC contracts, especially the Emerald Book 2019, address risk allocation and mitigation in underground construction projects.

Author:

11/13/2023


Panther Pounces on Late Notice: Dubai court disagrees with Obrascon on time-bar under Sub-Clause 20.1 of FIDIC 1999


Contractors who fail to issue FIDIC 1999 Clause 20.1 notices on time risk losing claims. A DIFC Court of Appeal ruling reinterprets the 28-day notice period, challenging the Obrascon case and tightening requirements for timely contractor notifications under FIDIC contracts.

Author:

07/05/2023


The Role of the FIDIC Observer in ICC Arbitrations on FIDIC contracts


The ICC informed a recent FIDIC Conference that draft awards […]

Author:


Be Nice to the Kid in the Corner: Brussels Cour de Cassation provides Charter for Overworked and/or lazy arbitrators


This article considers the court’s decision and implications in a case where an ICC Arbitral Tribunal Chair admitted that his Administrative Secretary drafted significant parts of the award, which was appealed as an unlawful delegation of authority.

Author:

07/04/2023


Soaring global construction costs under FIDIC: whose risk?


This article first appeared in IBA Construction Law International, Vol […]

Author: ,

04/19/2023


Page 2 of 6

Search

  • Filter by FIDIC Book Colour

  • Search by FIDIC Clause

  • Author

  • Filter by category/industry

Terms & Conditions

The content of the Knowledge Hub is not legal advice. You should always consult a suitably qualified lawyer regarding a particular legal issue or problem that you have. Please contact us if you require legal assistance.