The Employer’s Agent
The Engineer is deemed to act for the Employer and is essentially the Employer’s agent under the FIDIC Red Book 1999. He is not a wholly impartial intermediary, unless such a role is specified in the Particular Conditions, and there is no general obligation under the FIDIC Red Book 1999 for the Engineer to act independently or impartially. However, when he is required to make a determination under Sub-Clause 3.5, he is obliged to make it a fair determination and when he is obliged to issue an Interim Payment Certificate under Sub-Clause 14.6, or a Final Payment Certificate under Sub-Clause 14.13, he must fairly determine the amount due.
The Engineer is deemed to act for the Employer and is essentially the Employer’s agent under the FIDIC Red Book 1999. He is not a wholly impartial intermediary, unless such a role is specified in the Particular Conditions, and there is no general obligation under the FIDIC Red Book 1999 for the Engineer to act independently or impartially. However, when he is required to make a determination under Sub-Clause 3.5, he is obliged to make it a fair determination and when he is obliged to issue an Interim Payment Certificate under Sub-Clause 14.6, or a Final Payment Certificate under Sub-Clause 14.13, he must fairly determine the amount due1.
But, what does “fair” and “fairly” mean and does it compromise the Engineer’s role as Employer’s agent?
The key things to note about the Engineer
- The Engineer is appointed by the Employer.
- The Engineer is paid for by the Employer.
- The Engineer is deemed to act for the Employer.
- The Engineer may be one of the Employer’s salaried employees.
- The Employer may replace the Engineer (without giving reasons)2.
- The Engineer must carry out the duties assigned to him in the Contract.
- If the Engineer fails to perform his duties, this may be a breach of the Employer’s obligation under the Contract to have appointed an appropriate person.
- The Employer may impose a requirement that the Engineer obtains specific approval before exercising a particular power.
- Whenever the Engineer exercises a particular power for which the Employer’s approval is required, then the Employer shall be deemed to have given approval.
The Engineer is the Employer’s Agent
Agency occurs where a party is authorised to act as the representative of another. An agent may be appointed either expressly or impliedly by consent. Under Sub-Clause 3.1 of the 1999 FIDIC forms of contract, the Engineer is deemed to act for the Employer and thus authorised to act as the Employer’s representative, i.e. he is the Employer’s agent.
Therefore, (unless there is a Particular Condition to the contrary), when an Engineer makes a “fair determination” under Sub-Clause 3.5 or “fairly determines” the amount due in an Interim Payment Certificate under Sub-Clause 14.6, or Final Payment Certificate under Sub-Clause 14.13, he remains the Employer’s agent.
This is supported in the FIDIC’s Contract Guide (1st edition, 2000) which states (with emphasis added): “Under [the FIDIC Red Book 1999] or [the FIDIC Yellow Book 1999], the Employer is required to appoint the “Engineer”, who is to be named in the Appendix to Tender. The Engineer does not represent the Employer for all purposes. The Engineer is not authorised to amend the Contract, but he is deemed to act for the Employer as stated in subparagraph (a). The role of the Engineer is thus not stated to be that of a wholly impartial intermediary, unless such a role is specified in the Particular Conditions. If [the FIDIC Red/Yellow Book 1999’s] Engineer is an independent consulting engineer who is to act impartially, the following may be included in the Particular Conditions: At the end of the first paragraph of Sub-Clause 3.5, insert: “The Engineer shall act impartially when making these determinations.””
In the FIDIC Red Book 1999, FIDIC removed the express requirement for the Engineer to act impartially found in the previous form, and made a conscious and deliberate attempt to distance itself from the Anglo-Saxon concept that the Engineer’s duty to be impartial should be implied to reflect the fair and unbiased role of the Engineer as explained in the English House of Lords decision of Sutcliffe v Thackrath3 (considering the R.I.B.A. standard form of contract). This concept has been followed in subsequent English decisions such as those of Mr Justice Jackson in Costain v Bechtel4 (considering the N.E.C.2 form of contract) and Scheldebouw v St. James Homes (Grosvenor Dock) Ltd5. However, it is a concept that is not thought to be well understood or accepted internationally. In civil jurisdictions it is often asked how someone paid by one party (and therefore not independent) can act impartially as between Employer and Contractor.
Determinations
So, under the FIDIC Red Book 1999, must the Engineer maintain his role as the Employer’s agent when making a “fair determination” under Sub-Clause 3.5 or when he “fairly determines” the amount due in an Interim Payment Certificate under Sub-Clause 14.6 or Final Payment Certificate under Sub-Clause 14.13 and, if so, how? What do the words “fair” and “fairly” mean and do they compromise the Engineer’s role as Employer’s agent?
“Fair” is defined widely in the Oxford English Dictionary and includes (with emphasis added) at number 14(a): “Of conduct, actions, methods, arguments, etc.: free from bias, fraud, or injustice; equitable; legitimate, valid, sound.”
“Fairly” is also widely defined and includes (with emphasis added):“1. In a fair manner, so as to be fair….4. (a) By proper or legal means; legitimately; in accordance with rules or laws… (b) In accordance with what is right or just; equitably; without bias, impartially. Also: with good reason, rightfully….5. In a proper or suitable manner; appropriately, fittingly; (also) proportionately…6. Clearly, distinctly, plainly; frankly, openly….”
Reference is made to the Oxford English Dictionary as it is a well-regarded and accepted authority on the English language, which is the official language of the FIDIC forms of contract. Obviously, not everyone will accept this source. However, from these definitions, it is logical to conclude that the Engineer is obliged to act without bias and impartially when making determinations under Sub-Clauses 3.5, 14.6 and 14.13, notwithstanding his role as Employer’s agent.
This conclusion is supported in other parts of the FIDIC Red Book 1999 General Conditions of Contract. If it were not the case:
- Why would the Engineer (as Employer’s agent) need to consult with both parties before reaching a determination?
- Why would the Employer be entitled to dispute the Engineer’s determination and refer it to the Dispute Board under Sub-Clause 20.4 (particularly if the Employer’s specific approval has been sought prior to issuing the determination)?
- How could the determination be disputed under the FIDIC form if the Contractor and the Engineer (as Employer’s agent) agreed? Ordinarily, if a principal does not like something his agent has done which was properly within the agent’s authority, the principal would take it up with the agent under the agency agreement.
The conclusion is also supported in the FIDIC Code of Ethics which states: “The consulting engineer shall: – Be impartial in the provision of professional advice, judgement or decision…”
The wording of the FIDIC Contracts Guide might be interpreted to compliment such a view. On one reading, the phrase “The role of the Engineer is thus not stated to be that of a wholly impartial intermediary…” could allow room for the Engineer to act as an impartial intermediary in limited situations, such as when making fair determinations under Sub-Clauses 3.5, 14.6 and 14.13.
An Engineer’s professional codes of conduct could also be relevant in establishing the way in which he is expected to behave. For example, the Guidance Notes on the Interpretation and Application of the Rules of Professional Conduct of the Institution of Civil Engineers state (with emphasis added): “Rule 1: All members shall discharge their professional duties with integrity and shall behave with integrity in relation to all conduct bearing upon the standing, reputation and dignity of the Institution and of the profession of civil engineering. The manner in which members can fulfil this Rule includes, but is not limited to, the following: -Carry out their professional duties with complete objectivity and impartiality.”
The FIDIC White Book 2006 goes further and refers to independence, although the obligation is not mandatory. Sub-Clause 3.3.2 states: “Where the Services include the exercise of powers or performance of duties authorised or required by the terms of a contract between the Client and any third party, the Consultant may: … (b) if authorised to certify, determine or exercise discretion to do so fairly between the Client and third party not as an arbitrator but as an independent professional exercising his judgement with reasonable skill, care and diligence;…”
The problem has been recognised in the pre-release version of the FIDIC Yellow Book 2017. In Sub-Clause 3.2 of the FIDIC Yellow Book 2017 (as in Sub-Clause 3.1 of the FIDIC Yellow Book 1999), the Engineer is still deemed to act for the Employer, i.e. he remains the Employer’s agent, except as otherwise stated in the Conditions. However, to remove any ambiguity as to how the Engineer should act when brokering agreements or making determinations, Sub-Clause 3.7 states, “The Engineer shall act neutrally between the Parties when carrying out duties under this Sub-Clause”. Siobhan Fahey of the FIDIC Contract Committee acknowledges that the words “fair” and “fairly” are causing problems around the world and she hopes that the new obligation on the Engineer to act “neutrally”, when making a fair determination under Sub-Clause 3.7, will resolve this issue. However, there is a risk that neutrally may be seen as a synonym for impartially used in previous editions which could see the opening up of old arguments6.
Note also that in the pre-release version of the FIDIC Yellow Book 2017, Sub-Clause 14.6.1 obliges the Engineer to issue an Interim Payment Certificate (“IPC”) stating the amount which he “fairly considers to be due” to the Contractor (and not the amount which he “fairly determines to be due” as in the FIDIC Red Book 1999). A similar change has been made in Sub-Clause 14.13 in respect of the Final Payment Certificate (“FPC”). This takes the issue of IPCs and FPCs outside the scope of Sub-Clause 3.7 and the Engineer’s obligation to act neutrally in the first instance. However, if the Contractor is not satisfied with an IPC, he may refer it to the Engineer for a determination. There seems to be no corresponding provision in respect of FPCs.
Unfortunately, the pre-release version of the FIDIC White Book 2017 is difficult to reconcile with the pre-release version of the FIDIC Yellow Book 2017 as it obliges the Engineer to act independently. Mandatory language is now used. Sub-Clause 3.9.3 states, “…If the Consultant is authorised under the Works Contract to certify, determine or exercise discretion in the discharge of its duties then the Consultant shall act fairly as go between [sic] the Client and the [C]ontractor, exercising independent professional judgement and using reasonable skill, care and diligence”.
Employer’s approval
The position is further complicated where the Engineer is obliged to obtain the Employer’s approval before, for example, agreeing or determining an extension of time and/or additional costs, or issuing Variations (under the FIDIC Red Book 1999 Particular Conditions or as set out in Sub-Clause 3.1 of the FIDIC Pink Book 2010). Under Sub-Clause 3.5 the Engineer is obliged to make a fair determination, but if the Employer does not approve that fair determination, the Engineer cannot make it. This leaves the Engineer in a very difficult position. He should not make a determination he thinks unfair but as the Employer’s agent he ought to do as he is told by his principal.
In practice, what appears to happen is that the Engineer does nothing and the matter is referred to the Dispute Board to resolve where a Dispute Board is provided for. Sub-Clause 20.1 of the FIDIC Pink Book 2010 states that “If the Engineer does not respond within the timeframe defined in this Clause7, either Party may consider that the claim is rejected by the Engineer and any of the Parties may refer to the Dispute Board in accordance with Sub-Clause 20.4”.
However, it is arguable that, by failing to approve the fair determination, the Employer has interfered with, or prevented, the Engineer from carrying out the duties assigned to him in the Contract . If done unreasonably, this may be considered a breach of contract by the Employer. Further, if the contract machinery for extending time for Employer risk and shared risk events is rendered inoperable by such an act of prevention, time may be set at large, entitling the Contractor to a reasonable time within which to complete the Works and defeat any claim for liquidated damages. This may happen if, for example, there is no recourse to a Dispute Board because one has not been appointed by the date stated in the Appendix to Tender (under the FIDIC Red Book 1999) or Contract Data (under the FIDIC Pink Book 2010).
Conclusion
The lack of clarity concerning the Engineer’s role in the FIDIC form has been criticised since 1999, and it is obvious to see why. Employers generally wish to have full control over their agents, whilst Contractors are concerned that the Engineer’s determinations will naturally favour the Employer. As currently drafted, this can cause problems for all concerned. Whilst the problems have been recognised in the pre-release version of the FIDIC Yellow Book 2017, the requirement upon the Engineer to act “neutrally” when making a determination is likely to raise many more questions. Further, an increase in payment disputes is to be predicted where the Engineer is obliged to issue Interim Payment Certificates and Final Payment Certificate fairly but not neutrally.
1There is no express obligation of fairness in any other contractual provision including, for example, Taking-Over under Sub-Clause 10.1.
2Although the Employer may not replace the Engineer with a person against whom the Contractor raises reasonable objection.
3[1974], AC 727. Lord Reid at page 737: “The building owner and the contractor make their contract on the understanding that in all such matters the [Engineer] will act in a fair and unbiased manner and it must therefore be implicit in the owner’s contract with the [Engineer] that he shall not only exercise due care and skill but also reach such decisions fairly, holding balance between his client and the contractor”. Lord Morris at pages 740-741: “Being employed and paid by the owner [the Engineer] unquestionably has in diverse ways to look after the interests of the owner. In doing so he must be fair and he must be honest. He is not employed by the owner to be unfair to the contractor”.
4[2005] EWHC 1018 (TCC).
5[2006] EWHC 89 (TCC).
6“Neutral” is defined in the Oxford English Dictionary as “Not belonging to, associated with, or favouring any party or side”. “Impartial” is defined similarly in the Oxford English Dictionary as “Not partial; not favouring one party or side more than another; unprejudiced, unbiased, fair, just, equitable. (Of persons, their conduct, etc.)”.
742 days.
8Roberts v Bury Improvement Commissioners [1870] L.R. 5 C.P. 310 – Blackburn J. “…it is a principle very well established at common law, that no person can take advantage of non-fulfilment of a condition the performance of which has been hindered by himself …; and also that he cannot sue for a breach of contract occasioned by his own breach of contract…”.Murphy’s Law
Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.
Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd,[1]. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.
The key facts
- The case concerned an amended FIDIC Yellow Book 1999.
- The Works were delayed. The Contractor (J Murphy & Sons Ltd.) failed to reach a Milestone and no extension of time was granted by the Engineer (Capita Symonds).
- The Employer (Beckton Energy Ltd.) notified the Contractor of its entitlement to delay damages with express reference to Sub-Clause 2.5.
- The Employer, who was in financial difficulties at the time, then gave 23 days’ notice of his intention to call on the bond for the Contractor’s failure to pay the delay damages within 30 days as required by a heavily amended Sub-Clause 8.7.
- The Contractor sought a declaration from the Court that (i) the Employer was not entitled to delay damages under the amended Sub-Clause 8.7 without agreement or determination by the Engineer under Sub-Clauses 2.5 and 3.5, and that (ii) any call on the bond by the Employer would be fraudulent (for which injunctive relief would then be sought).
Employer’s claims generally
Sub-Clause 2.5 was largely un-amended and sets out the procedure to be adopted where the Employer considers himself entitled to payment under any clause of the contractual conditions or otherwise in connection with the Contract (for example, for breach of contract). It is drafted widely, and one would ordinarily read it to include any claim for payment for delay damages under Sub-Clause 8.7.
It stated (with emphasis added):
“2.5 Employer’s Claims
If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract … the Employer or the Engineer shall give notice and particulars to the Contractor…The particulars shall specify the Clause or other basis of the claim, and shall include substantiation of the amount and/or extension to which the Employer considers himself to be entitled in connection with the Contract. The Engineer shall then proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the amount (if any) which the Employer is entitled to be paid…This amount may be included as a deduction in the Contract Price and Payment Certificates…”
The Employer’s entitlement to delay damages
Unfortunately, Sub-Clause 8.7 was so heavily amended that it is unrecognisable. It was badly done, with the interchangeable use of the terms delay damages and liquidated damages, and most crucially the deletion of the terms that the obligation to pay delay damages be “subject to Sub-Clause 2.5”. Better drafting would almost certainly have avoided the litigation. As mentioned above, Sub-Clause 2.5 expressly states that it applies where the Employer considers himself entitled to payment under any clause of the contractual conditions, but in the absence of any clear wording to the contrary would Sub-Clause 2.5 still apply (autonomously) where express reference to it in a particular clause has been deleted? The situation was so confusing that the Employer gave notice under Sub-Clause 2.5 despite later asserting that Sub-Clause 2.5 did not apply.
The un-amended Sub-Clause 8.7 states:
“8.7 Delay Damages
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay delay damages to the Employer for this default…”
As amended, it stated:
“8.7 Delay Damages and Bonus
8.7.1 If the Contractor fails to:
a) achieve the ROC Acceditation Milestone by the ROC Accreditation Date the Contractor shall pay or allow to the Employer liquidated damages for such delay at the daily rate of £4,000 for each day commencing from the ROC Accreditation Date until the earlier of the achievement of i) the ROC Accreditation Milestone or ii) 31 March 2015; and
b) achieve the ROC Accreditation Milestone by the ROC Eligibility Change Date the Contractor shall pay or allow to the Employer a Bullet Payment; and
c) achieve the Taking-Over Date for the Works within the Time for Completion,
the Contractor shall pay or allow to the Employer liquidated damages for delay. Such liquidated damages shall be payable at the daily rate of £23,000 for each day after the Time for Completion for the Works up to and including the Taking-Over Date for the Works…
8.7.4 Delay damages due pursuant to this Sub-Clause 8.7 shall be deducted from the next applicable Notified Sum following the end of the month in which such delay occurred or where no such Notified Sum is applicable or is disputed, shall be payable within 30 days of the end of the week in which such delay occurred.”
The “Notified Sum” was another amendment to the standard form contract and was simply a sum stated by the Contractor with no reference to the Engineer.
The Employer’s entitlement to call the bond
Sub-Clause 4.2 was also heavily amended and also deleted reference to Sub-Clause 2.5. Apparently, the Employer’s lender had insisted on a non-negotiable procedure whereby any claim on the bond would not be subject to any kind of restriction or procedure that would give rise to delay in payment under it.
The un-amended Sub-Clause 4.2 states:
“4.2 Performance Security
The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract in the event of … (b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under Sub-Clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination …”
As amended, it stated:
“4.2 Performance Security…
4.2.5 The Employer shall give …23 days’ prior written notice to the Contractor of its intention to make a demand under the [Bond] stating the breach the Contractor has committed, during which period and without prejudice to the Employer’s entitlement and discretion to claim under the relevant Performance Security at the expiry of the said 23 days, the Contractor may seek to remedy the relevant default and/or breach… .
4.2.6 If and to the extent i) the Employer was not entitled to make a claim under the Performance Security and/or ii) amounts recovered under any claim under the Performance Security exceed the entitlements and/or otherwise exceed the losses suffered and recoverable by the Employer under the Contract, the Employer shall be liable for and reimburse the Contractor such excess amounts.”
Findings
Mrs Justice Carr found that while, on its face, Sub-Clause 2.5 was drafted in the widest possible terms[2], in this case the right to delay damages under Sub-Clause 8.7 (as amended) was not subject to the Engineer’s determination under Sub-Clauses 2.5 and 3.5 for the following reasons:
- The wording “subject to Sub-Clause 2.5” had been deleted from the amended Sub-Clause 8.7. Objectively assessed on the facts, this selected deviation from the standard form was consistent with the parties’ intention being not to make the Employer’s right to delay damages subject to Sub-Clauses 2.5 and 3.5.
- The amended Sub-Clause 8.7 set out a self-contained regime for the trigger and payment of delay damages.
- There were important and substantive differences between Sub-Clause 2.5 and the amended Sub-Clause 8.7, which were resolved if the amended clause was not subject to Sub-Clause 2.5. For example, amended Sub-Clause 8.7 referred to payment by way of deduction from the Notified Sum, whereas Sub-Clause 2.5 referred to payment by way of deduction from Payment Certificates.
- As Sub-Clause 2.5 appeared not to have been properly thought out in the full context of the Contract (viz the reference to Payment Certificates not the Notified Sum), this undermined the weight to be attached to it.
- The tension that existed between Sub-Clause 2.5 and the amended Sub-Clause 8.7 did not exist between Sub-Clause 2.5 and other sub-clauses.
The fact that the Employer had given notice in accordance with Sub-Clause 2.5 was not a point of substance as there was no suggestion of any relevant waiver, estoppel or election.
Mrs Justice Carr also found that under the amended Sub-Clause 4.2, the bond was a conventional on-demand bond. Any call on the bond to recoup the delay damages would not be fraudulent provided the Employer simply believed that it was entitled to delay damages under the amended Sub-Clause 8.7 even though there had been no agreement or determination of that entitlement under Sub-Clauses 2.5 and 3.5.
Commentary
An Employer’s notice under Sub-Clause 2.5 is expressly required in some 14 different sub-clauses of the un-amended FIDIC Yellow Book. As a result of this decision, where reference to Sub-Clause 2.5 in a sub-clause has been omitted and the Employer believes he is entitled to payment or an extension of the Defects Notification Period, the Employer may now not need to give notice under Sub-Clause 2.5 despite its wide wording “If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract”, and the desirability of the notice. This is consistent with the normal principles of freedom to contract where there are commercial parties of roughly equal bargaining strength. The English courts will not re-write a contract.
Comparisons might be drawn with the Contractor’s notice under Sub-Clause 20.1 which is expressly required in some 18 sub-clauses of the un-amended FIDIC Yellow Book. If reference to Sub-Clause 20.1 in a sub-clause has been omitted and the Contractor believes he is entitled to additional time or money, would the Contractor not need to give notice under Sub-Clause 20.1? Under English law, it will depend upon the parties’ intention by reference to what a reasonable person (having all the background knowledge which would have been available to the parties) would have understood the parties to be using the language in the contract to mean[3]. In the case of a clear and irreconcilable discrepancy, more weight will be given to the particular or amended conditions over the general standard form printed conditions[4].
Where Sub-Clause 20.1 has been (i) omitted, or (ii) where there has never been reference to Sub-Clause 20.1 in a sub-clause (for example in the variation provisions at Sub-Clauses 13.1 to 13.6), and the Contractor believes he is entitled to additional time or money, one would still ordinarily recommend that notice be given under Sub-Clause 20.1 because of the wide wording of Sub-Clause 20.1 “If the Contractor considers himself to be entitled to any …additional payment, under any Clause of the Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer….”, and the obvious desirability of notice of alleged variations. However, the Howard Kennedy International Construction team (formerly Corbett & Co.) does have experience of a Dispute Adjudication Board refusing to dismiss a variation claim for want of a Sub-Clause 20.1 notice.
It is probably right that notice regimes ought only to be applied where they are very clear, given the serious effect they may have on what could otherwise be good claims. This is a philosophy reflected by Mr Justice Akenhead in Obrascon Huarte Lain SA -v- Her Majesty’s Attorney General for Gibraltar[5].
Conclusion
In summary, Sub-Clauses 8.7 in its un-amended FIDIC Yellow Book form is expressly subject to Sub-Clause 2.5, so that the Engineer will agree or determine the delay damages payable by the Contractor to the Employer. Similarly, Sub-Clause 4.2(b) in its un-amended FIDIC Yellow Book form is expressly subject to Sub-Clause 2.5, so that in order to claim under the Performance Security for amounts due an Engineer’s determination may be required. Provided these clauses have not been amended there is no ambiguity.
Whilst this case is specific to the particular contractual amendments, it does serve as a warning to anyone involved in amending the standard form FIDIC contracts or considering a claim under an amended standard form FIDIC contract to consider closely the interplay between the contractual provisions.
[1] [2016] EWHC 607 (TCC).
[2] See: NH International (Caribbean) Ltd v National Insurance Property Development Company Ltd [2015] KPC 37.
[3] Assessed using the six factors set out in Arnold v Britton [2015] UKSC 36 namely: (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions, (iii) the overall purpose of the clause and the contract, (iv) the facts and circumstances known or assumed by the parties at the time that contract was made, and (v) commercial common sense, but (vi) disregarding subjective evidence of any party’s intentions.
[4] Homburg Houtimport BV v Agrosin Private Ltd (the ‘Starsin’) [2003] UKHL 12.
[5] [2014] EWHC 1028 (TCC).The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading
In this article Corbett & Co. Director Andrew Tweeddale addresses whether sub-clause 20.5 is a condition precedent to the commencement of an arbitration or whether it is an obligation, the breach of which will not affect the jurisdiction of the arbitral tribunal to resolve the dispute.
This article addresses whether sub-clause 20.5 is a condition precedent to the commencement of an arbitration or whether it is an obligation, the breach of which will not affect the jurisdiction of the arbitral tribunal to resolve the dispute.
Click here to read the full article originally published in The International Construction Law Review in 2016.
