• Time’s up for FIDIC’s Pink Book?

    Rumour reaches us that the Multilateral Development Banks (MDBs) behind the Pink Book, FIDIC’s harmonised version of the 1999 Red Book, will discontinue the experiment. Should we be sorry to see the back of the Pink Book? We think not.

    Rumour reaches us that the Multilateral Development Banks (MDBs) behind the Pink Book, FIDIC’s harmonised version of the 1999 Red Book, will discontinue the experiment. Should we be sorry to see the back of the Pink Book? We think not.

    The idea would be to return to the Red Book with each MDB developing its own particular conditions.

    The fragile consensus between the banks was already unravelling: the 2010 edition already had six bank-specific versions of clauses 15.6 to 16.2 on the subject of bribery and corruption.

    The creations of committees are notoriously odd. The more independent and strong-willed the representatives of the committees, the odder will be the result. MDBs – and there were nine of them involved in the first version in 2005 – can be notoriously stubborn. So it would be no surprise to learn that their amendments to the Red Book produced some oddities.

    However, to be fair, the Pink Book also gave birth to some interesting ideas which FIDIC would do well to consider when drafting the 2nd editions of the Red, Yellow and Silver Books, a process now under way.

    Below we consider a sample of both MDB oddities and also some it its good ideas.

    Oddity #1: Contractor Control of the Commencement Date

    The “stand-out” oddity relates to the Commencement Date. The amendments to clause 8.1 effectively put the Contractor in charge of when both work and the Time for Completion start. The Commencement Date can only be given when both parties have agreed that four precedent conditions have been fulfilled. Two of these are under the control of the Contractor, namely the signature of the Contract Agreement by the Contractor and the payment of the advance payment which depends on the provision by the Contractor of the advance payment guarantee.

    The result is that if it benefits a Contractor to delay the start date – for example to give himself additional mobilisation time or in order to avoid a winter period – he can do so simply by delaying provision of the guarantee.

    Better still for the unscrupulous, if the notice and instruction to commence are not provided within 180 days, the Contractor can terminate for Employer default and claim his lost profit on the job! This is apparently so even if the delay was due to the Contractor withholding his guarantee.

    Of course, legal systems would resist this extraordinary result. Good faith doctrines would no doubt be mobilised in the civil law world to try to prevent a windfall result. Prevention principles might help out the Employer.

    The question is: what were the draftsmen thinking when they added this to the MDB form? It was not in the original 2005 edition. And: who was lobbying the MDBs on behalf of contractors? They plainly did a very good job.

    Good Idea #1: Define the Term “Profit”

    The Pink Book defines as 5% the profit to which the Contractor is entitled as part of “Cost plus profit”. This avoids the 10 instances of “reasonable profit” that appear in the Red Book with all the accompanying room for uncertainty and argument. (Should “reasonable profit” be based on any profit figures in the contract, or the Contractor’s tender calculations, or current market profit levels or the Contractor’s own average historical profitability or indeed the profitability of the particular project?)

    There are 71 “reasonables” and “reasonablys” plus two “unreasonablys” still left to argue about but the MDBs have taken a step in the right direction.

    Oddity #2: The Contractor Chooses his Bonding Bank

    The contractors’ lobby appears to have succeeded regarding bonds and guarantees. Clauses 4.2 and 14.2 have been amended so that contractors can provide performance and advance payment guarantees from any “reputable bank or financial institution selected by the Contractor”. The same applies to retention bonds which, by clause 14.9, the Contractor is entitled to substitute for a cash retention on taking-over.

    As the MDBs know better than most, the value of bonds does not depend only on the repute of the bank but also on the attitude of the courts. The courts appear to be very willing to intervene on behalf of a contractor to block payment. Other countries have the same problem – or safeguards – depending on your point of view.

    The fact is that if the point of the bond is to provide security nearly equivalent to cash in hand, or at least security obtainable “on demand”, then it matters where it comes from. Employers should be careful to ensure that the bond will be readily cashable. These amendments effectively prevent that. It is particularly odd that amendments made by funders for their client Employers should insist on bonds in lieu of cash retention; and then undermine the value of those bonds.

    Good Idea #2: A Timescale for the Engineer’s Determination

    The obligation on the Engineer to make determinations promptly is specified in clause 3.5. He has 28 days. The consequence of not making a determination in relation to a claim within 42 days is spelt out in clause 20.1: the claim may be treated as rejected and the matter may be referred to the dispute board. This is a welcome clarification: it was generally understood that silence could be treated as a rejection; but there was much room for argument as to the required length of the silence and the effect of a late determination.

    Oddity #3: Contractor Receives Profit if Project Cancelled

    It is odd that the MDBs should volunteer that Employers who cancel the project and terminate for convenience under clause 15.5 should have to compensate contractors for their lost profit as if the termination were a default.

    The 1999 editions – and, I would imagine, the 2nd editions will do the same – require Employers to refund to Contractors their costs and pay for their demobilisation but they do not award profit. It was accepted that Contractors signing FIDIC contracts took the risk that their clients might cancel the project for one reason or another. An omission is a cancellation of part only of the project: however, here the Pink Book does not award lost profit on the omitted work.

    Clause 16.4 no longer refers expressly to loss of profit but there can be little doubt that a right to be paid “the amount of any loss or damage suffered by the Contractor as a result of this termination” would include profit.

    Good Idea #3: Time Limit for Employer’s Claims

    The Red Book imposes tough time-limits and draconian sanctions on Contractor claims; but imposes neither on the claims of Employers. It seems right and a little more balanced to impose a time-limit on the Employer’s notices of claim. Even though there is no express sanction attached to a failure to notify, the 28-day obligation reduces the contrast between the regimes applying to Contractors and Employers.

    Conclusion

    Whether the Pink Book continues to a new edition or not, it has certainly produced some good ideas as well as some curiosities. Harmony may be desirable in general but perhaps not when it comes to standard forms.

    For a full list of the differences between the Red Book 1999 and the Pink Book 2010,click here

  • Can a party ignore FIDIC’s DAB process and refer its dispute directly to arbitration?

    If there is no DAB appointed by parties to a FIDIC 1999 contract, may disputes be referred directly to arbitration under Clause 20.8? This issue has troubled many in the industry – and has now been considered in English and Swiss courts.

    If there is no DAB appointed by the parties to a FIDIC 1999 contract, may disputes be referred directly to arbitration under clause 20.8? This issue has troubled many in the industry – and has now been considered in English and Swiss courts.

    Background to the issue

    Regular users of FIDIC contracts will be aware that the 1999 Red Book makes provision for a ‘standing’ DAB and the 1999 Yellow and Silver Books make provision for an ad-hoc DAB. In the Red Book, the pro forma appendix to tender provides the default position that the standing DAB should be constituted 28 days after the commencement date. In the Yellow and Silver books, the DAB is to be appointed by the date 28 days after one party gives notice to the other of its intention to refer a dispute to a DAB.

    It seems clear that it was intended by the drafters of all 1999 FIDIC books that a dispute, once crystallised, should be referred to the DAB prior to amicable settlement/arbitration under Sub-Clauses 20.5 and 20.6. However, in circumstances where this is not possible (e.g. if a party refuses to sign the dispute adjudication agreement (DAA) and the DAB is not ‘in place’), it was also intended by the drafters that the parties could rely on Sub-Clause 20.8 to bypass that process.

    In the author’s experience, it is common for parties to enter into a 1999 Red Book contract but fail to constitute the DAB in the time set out in the Appendix to Tender. It is also common in projects involving a Yellow or Silver Book contract to find that one party does not want to refer the matter to a DAB. That party might procrastinate in the DAB appointment process and, even if an appointment is eventually made by the appointing body under Sub-Clause 20.3, that party may then refuse to sign the DAA.

    There are conflicting views on whether an appointment under Sub-Clause 20.3 renders the signature of a DAA unnecessary. The author’s view has always been that only when the DAA is actually signed can a DAB be said to be ‘in place’. If that view is correct then (absent any ability by a court to rectify a refusal to sign – see below) it follows that Sub-Clause 20.8 can be relied upon and the dispute referred directly to arbitration. This view is supported by the FIDIC Contracts Guide Commentary on Sub-Clause 20.8:

    “There may be “no DAB in place” because of a Party’s intransigence (e.g., in respect of the first paragraph of P&DB/EPCT 20.2), or because the DAB’s appointment had expired in accordance with the last paragraph of Sub-Clause 20.2. If a dispute arises thereafter, either Party can initiate arbitration immediately (subject to the first paragraph of P&DB/EPCT 20.2), without having to reconvene a DAB for a decision and without attempting amicable settlement. However, the claimant should not disregard the possibility of settling the dispute amicably.

    Under P&DB or EPCT, the first paragraph of Sub-Clause 20.2 requires a DAB to be appointed within 28 days after a Party gives notice of intention to refer a dispute to a DAB, and Sub-Clause 20.3 should resolve any failure to agree the membership of the DAB. The Parties should thus comply with Sub-Clauses 20.2 and 20.3 before invoking Sub-Clause 20.8. If one Party prevents a DAB becoming ‘in place’, it would be in breach of contract. Sub-Clause 20.8 then provides a solution for the other Party, which is entitled to submit all disputes (and this breach) directly to arbitration.”

    If one party is simply not prepared to co-operate with what is intended to be a consensual DAB process, particularly in light of the difficulties that are now recognised with the enforcement of binding but not final DAB decisions, then it makes sense for the power in Sub-Clause 20.8 to be available and exercised.

    The courts of both England and Switzerland have had to consider these issues recently and both courts proceeded on the basis that there is a tension between:

    • the opening wording of Sub-Clause 20.2 which uses mandatory language for the parties to refer their dispute to the DAB; and
    • the wording in Sub-Clause 20.8 which provides that if a DAB is not ‘in place whether by expiry … or otherwise’ the parties can bypass the DAB.

    This tension is particularly apparent in the Yellow and Silver Books where the parties are to constitute an ad hoc DAB when a dispute has arisen. However, a literal reading of Sub-Clause 20.8 in isolation allows a party to bypass the DAB in favour of arbitration because necessarily no DAB will be ‘in place’ at that point.

    The English case: Peterborough City Council (“the Council”) v Enterprise Managed Services Limited (“EMS”)[1]

    The parties entered into a FIDIC Silver Book 1999 contract with amendments to Sub-Clause 20.6 which provided that the English courts would be substituted for arbitration. The Council opted to bring court proceedings without referring the matter to the DAB, relying on Sub-Clause 20.8. EMS applied for a stay of the court proceedings relying on Sub-Clause 20.2. Mr Justice Edwards-Stuart granted the stay for the parties to resolve their dispute in accordance with the contractual machinery i.e. to enable the dispute to be referred to the DAB.

    Counsel for EMS, Ms Anneliese Day QC, relied on the opening words of Sub-Clause 20.2 and pointed out that if the wording in Sub-Clause 20.8 were interpreted literally, it would render Sub-Clauses 20.2 to 20.5 redundant.

    Counsel for the Council, Ms Fiona Sinclair QC, relied on the words “or otherwise” in Sub-Clause 20.8 to argue that it could refer the matter to court in any circumstances where no DAB was ‘in place’. Counsel argued that the source of the DAB’s authority was the DAA (an important point that the judge agreed with); that without a signed DAA the DAB could not be ‘in place’; that because the parties had failed to sign the DAA, the route to arbitration under Sub-Clause 20.8 was open. To support her position that the court should allow court proceedings under Sub-Clause 20.8 (as opposed to insisting on reference to a DAB under Sub-Clauses 20.2 to 20.4), Ms. Sinclair argued that Sub-Clauses 20.2 to 20.4 were unenforceable anyway for lack of certainty as a result of the ‘gap’ identified in the FIDIC General Conditions by commentators.

    The judge considered the difficulties that exist in relation to the enforceability of binding DAB decisions as raised by Ms Sinclair. They had been set out in two articles on the “gap”. One was written by Professor Nael Bunni. The other was the present author’s own article entitled Mind the gap: Analysis of cases and principles concerning the ability of ICC tribunals to enforce binding DAB decisions under the 1999 FIDIC Conditions of Contract [2012] Int ALR 145. The judge summarised the issues set out in: “Mind the gap” as follows:

    “limitations on the powers of the arbitrators…(in particular whether or not they could order specific performance), the type of award (interim, partial or final) that is or may be appropriate if the DAB’s decision is to be enforced and the whole question of delay that would be involved in resorting to arbitration”.

    The judge considered that although this “may be arguable in the context of the standard FIDIC red books which include an arbitration clause, it loses force where the arbitration clause has been removed – as in the present case.” His rationale was that an English court has the power of specific performance and so would have no difficulty in using that power in relation to the enforcement of a DAB decision.

    The judge turned to the potential problem of a failure by the parties to agree on an adjudicator’s fees for insertion in the DAA. He found that there was an implied term that the adjudicator would be entitled to his reasonable fees and expenses which the court could readily assess in default of agreement. In practice, however, it is usual for the DAB to propose its own fees. If one party considered that the fees were reasonable and the other thought they were excessive and therefore refused to sign the DAA, it is unlikely that the court could impose a lesser fee than that requested by the DAB because in those circumstances, it is likely that the DAB would simply refuse to act.

    The judge dealt with the situation where one party refused to sign the DAA. He ruled that again, the court could exercise its power of specific performance to compel the refusing party to sign. Indeed, if all of the terms of the DAA were clear and accepted, and/or the court felt able to imply reasonable fees in the absence of agreement, the possibility of compelling a party to sign might be appropriate. However, in circumstances where, for example, the DAB wished to propose additional terms to its DAA (which is quite common in practice) and one party rejected those terms, it is questionable whether a judge would have the power to compel the parties to sign in the face of such disagreement.

    It is interesting to note that the judge considered that the DAB is ‘in place’ from the moment that the member(s) of the DAB has/have been appointed, whether under Sub-Clause 20.2 or 20.3. He considered that “the effect of incorporating the Appendix to the Conditions as the terms of the Dispute Adjudication Agreement was that all the relevant terms of that agreement would be in place save for agreement of the adjudicator’s fees”. The advantage of the judge’s analysis is that if there is an interval (which might be substantial) between the date of appointment and the date on which a party ultimately signs the DAA (following an order by the Court that it is compelled to sign), any work carried out by the DAB in this period will be within its jurisdiction. Conversely, if the date when the DAB is ‘in place’ is the date of signature of the DAA, any work carried out in the interval before date of signature would arguably be a nullity.

    The judge’s construction fits the facts of the Peterborough case because he concluded that he could rectify the issues set out above (failure to agree terms/fees/refusal to sign). However, his construction would not necessarily be correct in circumstances where those issues could not be rectified by the court or by an arbitral tribunal. The judge correctly concluded that the source of the DAB’s authority is the DAA. If specific performance is not a power available to the arbitral tribunal or if the nature of the issue is simply not amenable to the exercise of such a power, then the judge’s analysis is questionable.

    Swiss Federal Supreme Court Case dated 7 July 2014[2]

    The Parties entered into a FIDIC 1999 contract – the court did not specify which Book. Following a dispute the parties spent some 15 months unsuccessfully trying to form a DAB despite some input from the President of FIDIC. It is difficult from the judgment to establish the precise sequence of events. In the end, one party refused to sign the DAA and issued arbitration proceedings. As a preliminary issue, the arbitral tribunal was asked to determine whether it had jurisdiction over the dispute referred to it. The tribunal, seated in Geneva, issued a partial award upholding jurisdiction. The losing party sought annulment of the partial award in the Swiss courts, under ss. 190-192 PILA, the Swiss law on international arbitration. The Swiss Federal Supreme Court published its redacted judgment in French on 20 August 2014. It rejected the application for annulment upholding the arbitral tribunal’s partial award. This article relies on an unofficial translation of the judgement.

    Reasoning

    The following points mentioned in the judgment are of interest:

    • Reference to the DAB is mandatory subject to exceptions.
    • What was contemplated by Sub-Clause 20.8 was exceptional (for a standing DAB situation), namely there is a time-period for the duration of the DAB which then expires. In such circumstances, the DAB is no longer ‘in place’.
    • The strict interpretation of Sub-Clause 20.8 “would ultimately turn the alternate dispute resolution mechanism devised by FIDIC into an empty shell” (the same point made by counsel for EMS in the English case above).
    • The intransigence of a party was an example of circumstances that justify omitting the DAB.
    • Special circumstances, whether objective or not, must be reserved in which resorting to pre-arbitration DAB procedure could not be imposed upon the party wishing to submit the dispute with its contractual counterpart to arbitration. Considered from the opposite perspective, the exception is a case in point of the principle of good faith, which governs the procedural behaviour of the parties as well. Depending on the circumstances, the principle will therefore prevent one of them from objecting on the basis of the absence of a DAB decision. Yet, saying in advance and once and for all when it may be applied is impossible because the answer to the question depends upon the facts germane to the case at hand.”
    • Under Clause 2, first paragraph, of the General Conditions of the DAA, the DAA takes effect when the project owner, the contractor and each member of the DAB have signed it. On the facts of this case, as the DAA had not been signed, the DAB was not ‘in place’. In circumstances where a DAB is not ‘in place’, it is permissible to refer the dispute directly to arbitration under Sub-Clause 20.8.
    • [I]t is indeed impossible to blame the Respondent for losing patience and finally skipping the DAB phase despite its mandatory nature in order to submit the matter to arbitration.”

    It seems, therefore, that the Swiss court considered that Sub-Clause 20.8 was the exception rather than the rule. However, in the author’s view, that fact should not present a particular hurdle to its operation. If one party is faced with intransigence of another in the setting up of a DAB, it should not be necessary for him to waste further time proving that he did all he could to refer the matter to the DAB. The Swiss court did not give any guidance as to how long a party has to try for before it can resort to 20.8. Certainly, there was no endorsement of the 28-day time limit in 20.2 (which permits a party to apply to FIDIC) as the moment when 20.8 applies. The author suggests that as soon as the other party’s refusal to co-operate and therefore his breach of contract becomes clear, the first party should be free to refer the matter to arbitration. Necessarily at that point there will be no DAB ‘in place’ and so the mechanism in Sub-Clause 20.8 will be available. The Swiss court held that a refusal to sign the DAA meant there was no DAB ‘in place’ and so Sub-Clause 20.8 could be relied on. That decision must be correct even if the court left it unclear for how long such a refusal should last.

    Conclusion

    Both the English and the Swiss judgments support the existence of the DAB as the centre-piece for dispute resolution in the FIDIC contract. In England, the judge went so far as to treat the DAB process as a mandatory pre-condition to arbitration. The court felt able to rectify all the difficulties arising on the facts of that case by using its extensive powers to ensure that the DAB was ‘in place’. However, on other facts, even if an English court were substituted for arbitration, it is questionable whether it will always be possible to rectify a lack of agreement and/or signatures of the DAA. It is difficult to see how arbitrators could do so. Accordingly, it seems to the author that those who are prevented from referring a dispute to DAB by an uncooperative party may go directly to arbitration by relying on Sub-Clause 20.8. Those who would prefer to skip the DAB stage may not do so without first attempting to set up a DAB.

    In the second editions of the 1999 forms, FIDIC should consider making it clear that a failure by one party to sign the standard DAA with a DAB member agreed by the parties or appointed by FIDIC will not prevent the DAB giving valid decisions. To make this work, perhaps FIDIC could publish a range of fees deemed reasonable by any party signing a FIDIC contract. One way or another, the success of the DAB project depends on it being seen as a means of quick, straightforward, and enforceable dispute resolution. We are not there yet.

    Please get in touch at joanne.clarke@howardkennedy.com or victoria.tyson@howardkennedy.com with your thoughts or to discuss any concerns.

     

    [1] [2014] EWHC 3193 (TCC). http://www.bailii.org/ew/cases/EWHC/TCC/2014/3193.html.

    [2] 4A_124/2014. http://www.servat.unibe.ch/dfr/bger/140707_4A_124-2014.html.