Seminar: Introduction to International Arbitration in Construction & Engineering Disputes

Jo Clarke, in a webinar hosted by MBL Seminars, gives an introduction to international arbitration when used to resolve international construction and engineering disputes. It will include practical and tactical perspectives.

By |10/08/2025|featured, Knowledge Hub, Publications|Comments Off on Seminar: Introduction to International Arbitration in Construction & Engineering Disputes

FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC ‘launched’ the FIDIC 2022 reprints at the FIDIC International Construction Users’ Conference 2022, in London. The reception to the changes was mixed – some embraced the clarity; others questioned the significance and cost. This article draws your attention to 10 of the key areas of change in respect of the FIDIC Red Book 2017 including the definition of Claim, matters to be agreed or determined, the definition of Dispute and Exceptional Events.

By |18/01/2023|Design, Dispute Boards, featured, FIDIC, Knowledge Hub|Comments Off on FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

Price escalation and FIDIC: is Force Majeure an answer?

Could provisions in FIDIC contracts giving relief for ‘Force Majeure’ or ‘Exceptional Events’ provide relief to contractors suffering as a result of price escalation? It is well documented that construction and engineering projects around the globe are being affected by extreme and sometimes unprecedented price escalation. This is for many reasons including the Covid-19 pandemic and the Russo-Ukrainian conflict.

By |30/08/2022|Cost, featured, Knowledge Hub|Comments Off on Price escalation and FIDIC: is Force Majeure an answer?

FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

Up until the spring of 2020, a FIDIC 1999 Sub-Clause 13.7 [Adjustments for Changes in Legislation][1] claim was just one of many issues to be resolved, for example, in a delay and disruption claim or a Cost claim. However, the focus it receives in the context of Covid-19 is drastically different. Many in the industry are using the changes in legislation provision to seek financial compensation in a situation that would otherwise potentially only attract an extension of time.[2] Awarding Cost for Covid-19 events regardless of the circumstances may seem to some (Contractors mostly, though there are Employers and Engineers who agree) like the appropriate thing to do, but whether it is correct according to the Contract is a different question.

By |23/09/2021|Covid, Delay, featured, FIDIC, Knowledge Hub|Comments Off on FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

Changing Tack

A contract may require a party giving notice of a claim to specify the contractual or legal basis of that claim in the notice (or the supporting particulars). What if that party states a contractual or legal basis for the claim but later (perhaps with the benefit of additional information or because of advice from its lawyers) changes its mind or wants to include further contractual or legal bases? This was considered by the Hong Kong Court of Appeal in Maeda Corporation and China State Construction Engineering (Hong Kong) Limited v Bauer Hong Kong Limited [2020] HKCA 830. It found that a subcontractor could not change the contractual basis for its claim once the time period for providing such notice had expired. What, if any, impact will this decision have on the FIDIC forms of contract?

By |07/05/2021|Arbitration, featured, Knowledge Hub|Comments Off on Changing Tack

Jurisdiction, Admissibility and FIDIC

An issue that often arises in international arbitrations involving the FIDIC forms of contract is whether a claimant's failure to: (a) go through the dispute resolution provisions; or (b) comply with a time-bar clause gives rise to a question of admissibility or jurisdiction. Put another way, if a claimant has failed to issue a notice of claim within 28 days or failed to refer a dispute to a DAB, does the arbitral tribunal have jurisdiction to make an award on the merits or should the arbitral tribunal make an award stating that it lacks jurisdiction?

By |06/11/2020|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Dispute Boards, featured, FIDIC, Knowledge Hub|Comments Off on Jurisdiction, Admissibility and FIDIC

FIDIC’S Golden Principles – holding back the tide?

FIDIC is concerned about its image. It says that heavily amending the FIDIC forms of contract impacts upon the FIDIC brand and that this is damaging FIDIC’s reputation. It seeks to address this with the introduction of five Golden Principles. But the Golden Principles are merely aspirational; they are not binding and have no contractual effect. Does this render them a pointless gesture ‘trying to hold back the tide’?

By |10/03/2020|Dispute Boards, featured, FIDIC, Knowledge Hub|Comments Off on FIDIC’S Golden Principles – holding back the tide?

Pay attention Bond!

The recent English case Sumitomo Mitsui Banking Corporation Europe Limited v Euler Hermes Europe SA (NV) [2019] EWHC 2250 (Comm) highlights that where an on demand bond is assigned and a demand then made under that bond, the beneficiary will need to be sure not only that the demand is compliant with the terms of the bond but also that the assignment was effective in the first place.

By |10/03/2020|Bonds, English Law, featured, Knowledge Hub|Comments Off on Pay attention Bond!

FIDIC’s Emerald Book – A contractor’s charter or optimum risk allocation?

Is FIDIC’s new Emerald Book overly contractor-biased or does it offer pragmatic risk allocation for underground works? This article compares its benefits and risk distribution with the unamended FIDIC Yellow Book, especially regarding employer risks in claim-prone areas.

By |10/03/2020|Arbitration, featured, FIDIC, Knowledge Hub|Comments Off on FIDIC’s Emerald Book – A contractor’s charter or optimum risk allocation?

No EOT for Concurrent Delay, if so Agreed

Contract clauses that deny a contractor entitlement to an extension of time for concurrent delays caused by both employer and contractor are valid in principle.  In North Midland Building Ltd -V- Cyden Homes Ltd [1] the Court of Appeal of England and Wales has ruled that such clauses do not offend the common law prevention principle.  Nor do they give rise to an implied term to prohibit the imposition of delay damages that may result.

By |21/05/2019|Delay, English Law, featured, Knowledge Hub|Comments Off on No EOT for Concurrent Delay, if so Agreed

FIDIC contracts – What protection do they give contractors for employer financial problems?

In all construction contracts, one of the central principles is the Employer’s obligation to pay the contract price. The Contractor will be wary about the Employer’s financial standing and ability to pay and concerned to ensure that payments are made on time and that effective remedies are available in case of late or non-payment. The FIDIC standard forms of contract contain provisions dealing with these aspects.

By |21/05/2019|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC contracts – What protection do they give contractors for employer financial problems?

1999 Suite: Commentary on Clause 17 – Risk and Responsibility

Clause 17 covers risk and responsibility, indemnities, liability limitations, and intellectual property rights. The Contractor bears risk during execution and defect remedy periods, with risk transferring to the Employer upon issuing the Taking-Over Certificate. Risk allocation depends on governing law.

By |04/04/2019|Commentaries on the 1999 Suite, Delay, English Law, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 17 – Risk and Responsibility
Go to Top