1999 Suite: Commentary on Clause 16 – Suspension and Termination by Contractor

Clause 16 addresses suspension and termination by the Contractor, including rights to suspend work, grounds for termination, cessation of work, and payment on termination. It specifies notice periods, conditions for immediate termination, and entitlements following termination.

By |13/11/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 16 – Suspension and Termination by Contractor

1999 Suite: Commentary on Clause 12 – Measurement and Evaluation

FIDIC 1999 is a re-measurement contract, with the Employer bearing the risk of quantity variations. Clause 12 covers measurement, evaluation of rates, and valuation of omissions. It lacks a standard measurement method, which has been criticized.

By |13/11/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 12 – Measurement and Evaluation

1999 Suite: Commentary on Clause 09 – Tests on Completion

Clause 9 covers Tests on Completion, requiring the Contractor to give notice when ready to carry out Tests on Completion, addressing delays by either party, retesting after failure, and handling failures to meet contract requirements after retesting.

By |13/11/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 09 – Tests on Completion

1999 Suite: Commentary on Clause 04 – The Contractor

Clause 4 of the FIDIC Red Book 1999 consolidates various Contractor obligations, covering 24 topics. It includes general duties and references other significant obligations scattered throughout the Contract, such as communications, assignment, document care, compliance with laws, and time for completion.

By |13/11/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 04 – The Contractor

2017 Suite: Commentary on Clause 04 – The Contractor

Clause 4 changes include defining 'fitness for purpose' in Employer's Requirements, adjusting the Performance Security, handling communications by the Contractor's Representative, setting subcontracting limits, enhancing health and safety obligations, redefining unforeseeable conditions, and increasing Contractor risk for access routes.

By |13/11/2024|Commentaries on the 2017 Suite, Knowledge Hub|Comments Off on 2017 Suite: Commentary on Clause 04 – The Contractor

1999 Suite: Commentary on Clause 10 – Employer’s Taking Over

Clause 10 covers the Taking-Over of Works, Sections, or parts. It includes conditions for Taking-Over, deemed Taking-Over due to Employer's use or interference, and breach of contract if the Engineer fails to issue the Taking-Over Certificate.

By |25/04/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 10 – Employer’s Taking Over

1999 Suite: Commentary on Clause 20 – Claims, Disputes, and Arbitration

Clause 20 covers claims, disputes, and arbitration. It includes procedures for Contractor claims, appointing a Dispute Adjudication Board (DAB), handling disputes, amicable settlement, arbitration under ICC rules, and actions when a DAB decision is not complied with or absent.

By |24/04/2024|Adjudication / Dispute Boards / ADR, Arbitration, Commentaries on the 1999 Suite, Dispute Boards, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 20 – Claims, Disputes, and Arbitration

As simple as it seems? – an analysis of the prolongation costs clause in the FIDIC Green Book 2021

This article reflects on the introduction of an automatic contractual mechanism for calculating prolongation costs into the Green Book 2021 and will consider whether it will remove the expense of experts and lawyers from the process of claiming prolongation costs.

By |14/11/2023|Knowledge Hub|Comments Off on As simple as it seems? – an analysis of the prolongation costs clause in the FIDIC Green Book 2021

Risks in the Construction of Hydropower Projects: Unforeseen Ground Conditions under FIDIC

Hydropower projects rely heavily on ground conditions, which are often unpredictable despite pre-tender investigations. This article explores how FIDIC contracts, especially the Emerald Book 2019, address risk allocation and mitigation in underground construction projects.

By |13/11/2023|Knowledge Hub|Comments Off on Risks in the Construction of Hydropower Projects: Unforeseen Ground Conditions under FIDIC

Panther Pounces on Late Notice: Dubai court disagrees with Obrascon on time-bar under Sub-Clause 20.1 of FIDIC 1999

Contractors who fail to issue FIDIC 1999 Clause 20.1 notices on time risk losing claims. A DIFC Court of Appeal ruling reinterprets the 28-day notice period, challenging the Obrascon case and tightening requirements for timely contractor notifications under FIDIC contracts.

By |05/07/2023|Knowledge Hub|Comments Off on Panther Pounces on Late Notice: Dubai court disagrees with Obrascon on time-bar under Sub-Clause 20.1 of FIDIC 1999

Be Nice to the Kid in the Corner: Brussels Cour de Cassation provides Charter for Overworked and/or lazy arbitrators

This article considers the court's decision and implications in a case where an ICC Arbitral Tribunal Chair admitted that his Administrative Secretary drafted significant parts of the award, which was appealed as an unlawful delegation of authority.

By |04/07/2023|Knowledge Hub|Comments Off on Be Nice to the Kid in the Corner: Brussels Cour de Cassation provides Charter for Overworked and/or lazy arbitrators
Go to Top