Covid-19 and FIDIC contracts – what protections and entitlements?
Covid-19 has had huge consequences around the world and unfortunately
Covid-19 has had huge consequences around the world and unfortunately
Triple Point was a case heard in the English Court of
FIDIC is concerned about its image. It says that heavily amending the FIDIC forms of contract impacts upon the FIDIC brand and that this is damaging FIDIC’s reputation. It seeks to address this with the introduction of five Golden Principles. But the Golden Principles are merely aspirational; they are not binding and have no contractual effect. Does this render them a pointless gesture ‘trying to hold back the tide’?
In all construction contracts, one of the central principles is the Employer’s obligation to pay the contract price. The Contractor will be wary about the Employer’s financial standing and ability to pay and concerned to ensure that payments are made on time and that effective remedies are available in case of late or non-payment. The FIDIC standard forms of contract contain provisions dealing with these aspects.
Clause 17 covers risk and responsibility, indemnities, liability limitations, and intellectual property rights. The Contractor bears risk during execution and defect remedy periods, with risk transferring to the Employer upon issuing the Taking-Over Certificate. Risk allocation depends on governing law.
Clause 8 covers the start of works, time for completion, delays, extensions, and suspension of works. It includes provisions for commencement, completion, progress, delay damages, and suspension, with updates from the 4th Edition Red Book.
Clause 6 covers Staff and Labour, requiring the Contractor to comply with local laws, pay fair wages, provide accommodation, ensure health and safety, and maintain proper records. It also restricts recruitment from the Employer’s personnel and mandates qualified supervision.
Much has been said about the new Red, Yellow and Silver Books 2nd Editions launched by FIDIC in December last year. The most obvious comment has been about their size, almost 50,000 words, which is some 60% longer than the 1999 forms. Although the 1999 forms were not perfect, most regular users seem to be agreed that they did not need 20,000 words to fix the issues. This consensus led this author to attempt to cherry-pick the good bits from the 2017 forms and to propose amendments to add the good ideas to the 1999 forms. The amendments apply to all three forms unless it is indicated otherwise.
MT Højgaard is an important English case, considering fitness for purpose obligations in design-and-build contracts. This article examines the Supreme Court’s analysis of a fitness for purpose obligation in Højgaard and whether it would be applied to FIDIC’s Yellow Book contracts.
Much has already been written concerning the new FIDIC forms of contract published in December 2017. They are approximately 50 % longer and sought to set out the various procedure in much greater detail with the object of both encouraging good practice and reducing the scope for disputes. Numerous minor amendments have also been made. The purpose of this article is to look in more detail at the provisions dealing with Variations, these being amongst the most frequently scrutinised in practice.
Clause 14 covers payment aspects, including interim and final certificates, advance payments, retention monies, and the cessation of the Employer’s liability. It outlines the process for monthly payment applications, final settlement, and the Contractor's rights if payments are delayed.
Clause 3 outlines the Engineer's duties and obligations, including acting for the Employer, delegating authority (but not Determinations), issuing instructions, and handling Variations. It also covers Engineer replacement and making fair Determinations after consulting both Parties.
Corbett & Co. has published its selection of the best bits of the FIDIC 2017 2nd Editions adapted for use with the 1999 forms. With many people put off by the 50,000+ words of the new editions, the FIDIC 1999 Upgrade will permit users to benefit from FIDIC’s new ideas and improvements.
Clause 21 introduces a standing Dispute Avoidance/Adjudication Board (DAAB) instead of an ad-hoc DAB. The DAAB is appointed at the outset, assists in dispute avoidance, and its decisions are binding. The amicable settlement period is reduced to 28 days.
The new Clause 20 distinguishes between main Claims, which follow a strict procedure, and other Claims, which are determined by the Engineer without strict procedural requirements, starting from the disagreement between parties and requiring only a Notice of Claim.
Clause 18 replaces "Force Majeure" with "Exceptional Events," aiming for clarity in civil law jurisdictions. Strikes and lockouts are now distinct from riots. The clause maintains natural catastrophes and clarifies that invoking it results in contract termination.
Clause 16 introduces new grounds for suspension and termination, including non-compliance with binding decisions and non-receipt of Commencement Date Notice. It addresses corruption, and clarifies termination grounds and procedures. Contractors gain protection against financial consequences and can claim profit loss.
Clause 15 introduces new grounds for termination: non-compliance with a binding Engineer’s Determination or DAAB decision; and maxing out Delay Damages (actual deduction not necessary). Uncertainty remains if EOT is granted post-termination, potentially affecting the legality of termination.
Clause 10 changes include express references to As-Built Records, Manuals, and Training for Taking Over, a Notice of No-objection requirement, deemed Taking Over without these Notices, immediate issuance of Taking-Over Certificates, and a 14-day prevention period.
Contractors must prepare a detailed test programme reviewed by the Engineer. Clause 9.2 addresses delayed tests, applying Clause 10.3 for undue delays. Clause 9.2 adds procedures, including three Notices. Clause 9.4 expands failure criteria to include section rejection, complicating recovery under Clause 13.3.1.