2017 Suite: Commentary on Clause 09 – Tests on Completion
Contractors must prepare a detailed test programme reviewed by the Engineer. Clause 9.2 addresses delayed tests, applying Clause 10.3 for undue delays. Clause 9.2 adds procedures, including three Notices. Clause 9.4 expands failure criteria to include section rejection, complicating recovery under Clause 13.3.1.