1999 Suite: Commentary on Clause 04 – The Contractor

Clause 4 of the FIDIC Red Book 1999 consolidates various Contractor obligations, covering 24 topics. It includes general duties and references other significant obligations scattered throughout the Contract, such as communications, assignment, document care, compliance with laws, and time for completion.

By |13/11/2024|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 04 – The Contractor

2017 Suite: Commentary on Clause 04 – The Contractor

Clause 4 changes include defining 'fitness for purpose' in Employer's Requirements, adjusting the Performance Security, handling communications by the Contractor's Representative, setting subcontracting limits, enhancing health and safety obligations, redefining unforeseeable conditions, and increasing Contractor risk for access routes.

By |13/11/2024|Commentaries on the 2017 Suite, Knowledge Hub|Comments Off on 2017 Suite: Commentary on Clause 04 – The Contractor

FIDIC’s New Green Form: The Missing Link

In December 2021 FIDIC issued its 2nd edition of the Green Book. It is not so much an update to the 1st edition as a new and improved, intermediate form of contract. FIDIC is promoting it as a simpler, user-friendly alternative to the FIDIC 2017 Red and Yellow Books, where significant contract administration and management resources are not needed. The Green Book 2nd edition is recommended to be used by the World Bank for projects up to US$ 10 million. The Green Book 1st edition was originally intended for projects of US $500,000 with no more than a 6-month duration. However, the Green Book 1st was sometimes used for larger projects with a duration of up to two years. The Green Book 2nd therefore takes over from where the Green Book 1st left off. This is to be welcomed. The FIDIC 2017 suite of contracts (Red/Yellow/Silver) is unsuitable for smaller projects where less administration is required. The Green Book 2nd will therefore fill a much-needed gap in the FIDIC rainbow and is likely to be attractive to both Contractors and Employers. This article looks at some of the key features of the Green Book 2nd.

By |08/03/2022|FIDIC, Knowledge Hub|Comments Off on FIDIC’s New Green Form: The Missing Link

FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

Up until the spring of 2020, a FIDIC 1999 Sub-Clause 13.7 [Adjustments for Changes in Legislation][1] claim was just one of many issues to be resolved, for example, in a delay and disruption claim or a Cost claim. However, the focus it receives in the context of Covid-19 is drastically different. Many in the industry are using the changes in legislation provision to seek financial compensation in a situation that would otherwise potentially only attract an extension of time.[2] Awarding Cost for Covid-19 events regardless of the circumstances may seem to some (Contractors mostly, though there are Employers and Engineers who agree) like the appropriate thing to do, but whether it is correct according to the Contract is a different question.

By |23/09/2021|Covid, Delay, featured, FIDIC, Knowledge Hub|Comments Off on FIDIC Changes in Legislation and Covid-19: Compelled by Law or Just Doing Your Job?

1999 Suite: Commentary on Clause 06 – Staff and Labour

Clause 6 covers Staff and Labour, requiring the Contractor to comply with local laws, pay fair wages, provide accommodation, ensure health and safety, and maintain proper records. It also restricts recruitment from the Employer’s personnel and mandates qualified supervision.

By |14/11/2018|Commentaries on the 1999 Suite, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 06 – Staff and Labour

Variation Provisions in the FIDIC Yellow Book 2017

Much has already been written concerning the new FIDIC forms of contract published in December 2017. They are approximately 50 % longer and sought to set out the various procedure in much greater detail with the object of both encouraging good practice and reducing the scope for disputes. Numerous minor amendments have also been made. The purpose of this article is to look in more detail at the provisions dealing with Variations, these being amongst the most frequently scrutinised in practice.

By |29/10/2018|featured, Knowledge Hub|Comments Off on Variation Provisions in the FIDIC Yellow Book 2017

1999 Suite: Commentary on Clause 14 – Contract Price and Payment

Clause 14 covers payment aspects, including interim and final certificates, advance payments, retention monies, and the cessation of the Employer’s liability. It outlines the process for monthly payment applications, final settlement, and the Contractor's rights if payments are delayed.

By |26/09/2018|Commentaries on the 1999 Suite, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 14 – Contract Price and Payment

1999 Suite: Commentary on Clause 03 – The Engineer

Clause 3 outlines the Engineer's duties and obligations, including acting for the Employer, delegating authority (but not Determinations), issuing instructions, and handling Variations. It also covers Engineer replacement and making fair Determinations after consulting both Parties.

By |26/09/2018|Commentaries on the 1999 Suite, Dispute Boards, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 03 – The Engineer

2017 Suite: Commentary on Clause 08 – Commencement Delays and Suspension

Clause 8 changes include enhanced Programme requirements, Advance Warning mechanism, no Sub-Clause 20.2 notice for extension due to Variation, further definition of adverse climatic conditions, acceleration methods under Sub-Clause 13.3.1, and a cap on Delay Damages lifted for severe misconduct.

By |27/01/2018|Commentaries on the 2017 Suite, Delay, Knowledge Hub|Comments Off on 2017 Suite: Commentary on Clause 08 – Commencement Delays and Suspension

2017 Suite: Commentary on Clause 02 – The Employer

Clause 2 now comprises 6 sub-clauses. New provisions, 2.5 and 2.6, have been introduced. The obligations and consequences remain unchanged. In Clause 2.4, the Employer can now specify financial arrangements, and the Contractor can request evidence under specific conditions.

By |27/01/2018|Commentaries on the 2017 Suite, Knowledge Hub|Comments Off on 2017 Suite: Commentary on Clause 02 – The Employer

1999 Suite: Commentary on Clause 19 – Force Majeure

Clause 19 covers Force Majeure and release from performance, with broader definitions than typical laws. It prescribes detailed insurance requirements, reducing flexibility. The Contractor bears most obligations, necessitating careful amendments and professional advice to avoid misunderstandings and ensure proper incorporation into contracts.

By |28/09/2017|Commentaries on the 1999 Suite, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 19 – Force Majeure

1999 Suite: Commentary on Clause 15 – Termination by Employer

Clause 15 covers Termination by the Employer, including notices to correct, grounds for termination, valuation at termination, payment after termination, and the Employer's entitlement to terminate at will with 28 days' notice.

By |10/05/2017|Commentaries on the 1999 Suite, featured, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 15 – Termination by Employer

Murphy’s Law

Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.

By |03/10/2016|Bonds, Delay, English Law, Knowledge Hub|Comments Off on Murphy’s Law

1999 Suite: Commentary on Clause 05 – Nominated Subcontractors

Clause 5 defines a "nominated Sub-Contractor" and allows the Contractor to object on reasonable grounds. If the Employer insists on employing the Sub-Contractor, it must indemnify the Contractor. Payments to the Sub-Contractor are certified by the Engineer.

By |01/08/2016|Commentaries on the 1999 Suite, Knowledge Hub|Comments Off on 1999 Suite: Commentary on Clause 05 – Nominated Subcontractors
Go to Top