The Engineer under FIDIC forms of contract: Real-life questions
The 'Engineer' under the FIDIC forms of contract has long
The 'Engineer' under the FIDIC forms of contract has long
The Government of India has recently introduced important guidelines for
In August 2024 SIMC introduced a new Integrated Appropriate Dispute Resolution Framework ('INTEGRAF') to help disputing parties "unbundle disputes and apply the most appropriate dispute resolution mechanism to each aspect of a dispute." This article considers INTEGRAF's applicability in construction projects.
How do you establish whether a notice provision is really
Clause 2 outlines key Employer obligations, including access rights, assistance with permits, and financial arrangements. Additional obligations include payment (Sub-Clause 14.7) and taking over the Works (Sub-Clause 10.1). Employer claims require notice and compliance with Sub-Clause 2.5.
Will an oral agreement override a written one that expressly
A penalty is now to be regarded as: “a secondary
The purpose of the 1958 New York Convention is to
If an Employer sets off certified but unpaid sums without following Sub-Clause 2.5, it may breach contract terms under FIDIC 1999. This article explores whether Employers can bypass the Engineer’s role and why the clause’s wording is crucial to both Contractors and Employers.
The 1999 FIDIC forms of contract contain a number of
There is a substantial difference between the payment provisions of
Clause 1.15, previously in Sub-Clause 17.6 (1999 Edition), is now separated from Risk and Responsibility. It exempts parties from liability for loss, including loss of use, profit, or contracts, with exceptions for certain sub-clauses, notably Sub-Clauses 8.8 and 13.3.1(c).
Clause 14 outlines payment, certificates, and release from liability. While the methodology remains unchanged, procedural adjustments may delay payments but aim for prompt claim resolution. Some changes benefit contractors: e.g. claims are addressed during or shortly after the contract period.
Clause 13 clarifies the Engineer’s power to vary, allowing contractors to object to unforeseeable variations. Significant limitations include objections for health, safety, and environmental impacts. Variations must align with Employer’s Requirements, and supplemental agreements may be needed for significant changes.
Clause 12 covers Tests after Completion, often required for process and power contracts. Tests are conducted by the Employer, with significant changes including competent staff requirement, testing per Employer’s Requirements and O&M Manuals, and new provisions for test timing and notice.
Clause 11 has been clarified, with detailed provisions for notices and periods, DNP for Parts, and clearer time limits. Changes include risk allocation, compensation for denied access, and limited liability for Plant damage. Some cross-references may cause confusion.
Clause 7 of FIDIC 2017 mandates specified quality for plant, materials, and workmanship, requiring defect rectification. It covers testing, inspection, and rejection to ensure compliance. All sub-clauses have changed, with several significant modifications.
Clause 16 addresses suspension and termination by the Contractor, including rights to suspend work, grounds for termination, cessation of work, and payment on termination. It specifies notice periods, conditions for immediate termination, and entitlements following termination.
FIDIC 1999 is a re-measurement contract, with the Employer bearing the risk of quantity variations. Clause 12 covers measurement, evaluation of rates, and valuation of omissions. It lacks a standard measurement method, which has been criticized.
Clause 9 covers Tests on Completion, requiring the Contractor to give notice when ready to carry out Tests on Completion, addressing delays by either party, retesting after failure, and handling failures to meet contract requirements after retesting.