Unjust Enrichment and Construction Contracts – A Cinderella Story?
Two decades ago, unjust enrichment was described as “the Cinderella of law, barely 10 years old but growing up rapidly. Until recently unrecognised and overshadowed by the ugly sisters, Contract and Tort, Cinderella’s day has arrived.” In England a claim for unjust enrichment was initially referred to as a claim in ‘quasi contract’. This language has now been abandoned and unjust enrichment has a strong foothold in the landscape of commercial law and its role and limits are becoming more clearly defined. Despite this, it is only infrequently pleaded in construction cases and when argued it is often set out in broad terms where the facts do not support such a claim. However, this is cause of action that should not be overlooked by a contractor or employer – especially if they have claims that fall outside the four corners of their construction contract.
Murphy’s Law
Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.
The SCL’s New Take on the Delay and Disruption Protocol
In June of this year, the Society of Construction Law (“SCL”) sent its members a draft of the second edition of its widely recognised Delay and Disruption Protocol. It follows the publication of a Rider published late last year about which this author wrote a previous article. Although the “2016 Draft” is meant to be consultatory, there are a number of improvements from the “2002 Edition” worth exploring before the final and definitive version is published sometime in the future. There have been many changes not all of which will be covered in this article and, in any case, I will only focus on changes other than those already included in the Rider.
The Courtesy Trap – FIDIC’s Sub-Clause 20.5 – Amicable Settlement and Emirates Trading
In this article Corbett & Co. Director Andrew Tweeddale addresses whether sub-clause 20.5 is a condition precedent to the commencement of an arbitration or whether it is an obligation, the breach of which will not affect the jurisdiction of the arbitral tribunal to resolve the dispute.
1999 Suite: Commentary on Clause 05 – Nominated Subcontractors
Clause 5 defines a "nominated Sub-Contractor" and allows the Contractor to object on reasonable grounds. If the Employer insists on employing the Sub-Contractor, it must indemnify the Contractor. Payments to the Sub-Contractor are certified by the Engineer.
ICC Arbitration – Penalties for Slow Arbitrators
In its bulletin of 5 January 2016, the ICC announced penalties to encourage arbitrators to deliver up their awards more quickly than at present. The tardiness of some arbitrators has long been cause for major discontent amongst both lawyers and clients. Corbett & Co.’s worst experience was a sole arbitrator who took more than 18 months to issue an award on a preliminary issue!
Frozen Out
What relief does FIDIC provide when bank accounts are frozen as a result of war, hostilities, rebellion, terrorism etc.? Maybe not as much as you think. Tensions in Africa and the Middle East have seen the implementation of numerous international financial sanctions. While these sanction regimes vary in execution and enforcement they often freeze assets and prevent financial transactions. These restrictions may impact on the Employer’s performance of its payment obligations under the Contract. This can have serious consequences where the Contractor is entitled to suspend or terminate on notice for non-payment. Many parties automatically assume that financial sanctions will be recognised as force majeure. However, this may not be the case.
Where Do FIDIC Cases Go?
FIDIC is arguably the most widely used standard form of international construction contract but reported FIDIC cases are rare. Is it time for an increased publication of FIDIC cases? There are three categories of decisions arising out of FIDIC dispute resolution provisions: 1. Decisions of the Engineer or the Dispute Adjudication Board (DAB), which will generally not be published or reported to anyone other than the parties involved in the dispute. 2. Decisions of arbitral tribunals, which are not usually made public although this is subject to certain exceptions. 3. Decisions of national courts, which are a relatively rare occurrence for the reasons discussed below.
Society of Construction Law’s Rider 1 to its Delay and Disruption Protocol
In July of this year, the Society of Construction Law (SCL) published Rider 1 (“the Rider”) of its 2002 Delay and Disruption Protocol (“the Protocol”). The Rider’s Preamble lists a series of amendments to the Protocol intended to serve as an update reflecting (a) legal and industry practice developments, (b) feedback, (c) technological developments, (d) increase in scale of larger projects, and (e) international use of the Protocol. The Rider is intended to serve as the first part of the amendments to the Protocol, the totality of which should feature in a consolidated and updated version of the Protocol later this year.[1]
Employers Beware
How important is it for an Employer to give a Sub-Clause 2.5 notice of a set-off or cross-claim under the FIDIC Red Book form of contract? Very, according to the Privy Council in NH International (Caribbean) Limited v National Insurance Property Development Company Limited . It found that: o Sub-Clause 2.5 applies to any claims the Employer wishes to make. o The Employer must make such claims promptly and in a particularised form. o Where the Employer fails to raise a claim as required, the back door of set-off or cross-claims is firmly shut. The case also serves as a warning to Employers who take a relaxed view towards their obligation under Sub-Clause 2.4 to provide reasonable evidence of the financial arrangements they have made and are maintaining to pay the Contract Price. It doesn’t matter how wealthy or important the Employer is (it may be a Government, company or individual with very substantial funds) detailed financial information must still be provided.
Aspect v Higgins: The Final Reckoning
The English Supreme Court has ruled that losers in adjudications have six years to challenge an adjudicator’s decision from the payment date, while winners' rights to seek improvement end with the original claim's limitation period. This article considers the implications.
PERSERO 2 – Singapore Court of Appeal rules DAB decisions are enforceable by way of interim award
On 27 May 2015, the 160-page reserved judgement of the Singapore Court of Appeal (“CA”) was handed down in Persero 2 - PT Perusahaan Gas Negara (Persero) TBK (“PGN”) v CRW Joint Operation (“CRW”)[1]. It will be regarded a triumph for contractors wishing to enforce DAB decisions. The CA ruled that the interim award issued by the arbitral tribunal ordering enforcement of the DAB’s decision should stand. Using the concept of an “inherent premise”, the CA made two important findings: 1) it was not necessary for the Contractor to refer the failure to pay (the secondary dispute) back to the DAB; and 2) it was not necessary for him to refer the merits (the primary dispute) in the same single arbitration as his application to enforce.
Direct Claims by Subcontractors against Employers
A summary of contributions from around the world from members of the Cornerstone FIDIC Group on LinkedIn.
Court of Appeal confirms judgment in Obrascon v Gibraltar
The Judgment of Sir Robert Akenhead has been upheld and OHL’s appeals have been dismissed. The judgment was a rare excursion by the TCC into the FIDIC contract and considered unforeseen ground conditions, termination and notice under cl.20.1.
Time’s up for FIDIC’s Pink Book?
Rumour reaches us that the Multilateral Development Banks (MDBs) behind the Pink Book, FIDIC’s harmonised version of the 1999 Red Book, will discontinue the experiment. Should we be sorry to see the back of the Pink Book? We think not.
Time Waits for no Man – So you think the Adjudicator got it wrong? How long do you have to challenge the decision?
How long have you got to challenge the adjudicator’s decision? The English Court of Appeal has decided: 1) the claimant who considers the adjudicator awarded too little must challenge before the original limitation period for his claim expires; and 2) the defendant who considers he paid too much has a new limitation period starting on the day he paid the adjudicator’s decision. Is it unfair that the loser may have years longer than the winner? That question will soon be answered by the Supreme Court of the United Kingdom. Their decision will be of interest to anyone involved with FIDIC DABs anywhere in the world.
Comparison between the Red Book 1999 and the MDB Harmonised Edition Pink Book 2010
Read the full article here.
Can a party ignore FIDIC’s DAB process and refer its dispute directly to arbitration?
If there is no DAB appointed by parties to a FIDIC 1999 contract, may disputes be referred directly to arbitration under Clause 20.8? This issue has troubled many in the industry – and has now been considered in English and Swiss courts.
Indemnity Costs – you’ll be lucky! Interim Payment of Costs – definitely maybe
Even if a claimant has achieved complete success in litigation, it remains exceptionally difficult to recover legal costs on an indemnity basis, as this case demonstrates. Costs will most likely be recovered on the standard basis – at least in the absence of bad conduct during the litigation itself. This case also indicates that the court will generally limit an interim payment of costs to two-thirds of an approved costs budget.
Light at the end of the tunnel? Gibraltar dispute reviews key FIDIC Yellow Book provisions
As disputes under the FIDIC forms of contract are normally resolved in private Dispute Adjudication Board (“DAB”) proceedings or confidential arbitration proceedings, reported FIDIC cases are rare and often of considerable precdential value either formally or informally. In this article, originally published in The International Construction Law Review, Victoria Tyson considers one such recent decision which was transferred from the Gibraltar courts.